LGA · Getting started
Your first project, step by step
Create a practice renovation plan, check its budget and schedule, explore uncertainty, then download a report you can explain.
After sign-in, your private guided sample starts automatically. All sample prices and durations are synthetic teaching inputs.
Start here: three actions
1. Sign in
Choose Google, Facebook, or a text-message code. Use Create an account if you are new to phone sign-in.
2. Create the sample
On Projects, choose Try the guided sample. You will receive a private practice project with three cost lines and four activities.
3. Follow the instructions
On the project overview, choose Start lesson 1: Estimates. Each page shows what to do, what to expect and where to go next.
A separate historical example · caltrans-quantity-v1-20260918
Explain an estimate revision
Three historical Caltrans bid lines from January 2025, followed by a controlled quantity change. Prices are unadjusted to today's market.
Sign in with Continue with Google, open a private practice project, and go to Estimates. Facebook and SMS remain alternatives; use the same account when returning.
Try historical example
Expected result. Confirm Add example to this project. The Before baseline has three lines totaling $47,840.
If this step does not work
Check project access and wait for confirmed creation; use Check save status after a lost response.
Create editable revision
Expected result. A new Proposed version copies the baseline with new row IDs and shared lineage. The Before version stays unchanged.
If this step does not work
Select the intended Before version. A locked original can still be cloned when your role permits it.
Edit Proposed
Expected result. Edit CLASS 2 AGGREGATE BASE: quantity 56 → 62 CY, unchanged unit rate $715.00. Save the line, then Refresh comparison.
If this step does not work
Finish or discard the open line editor before saving review work. Correct field errors without losing the values you entered.
Check changes
Expected result. Before $47,840 → Proposed $52,130; base change +$4,290. Expand the row: the quantity effect explains six more CY at the unchanged historical rate.
If this step does not work
If sources changed, check updated rows and acknowledge them. Unknown units, currency or matches stay unresolved.
Save draft
Expected result. Private notes, chosen versions and row decisions are saved only after the server confirms. My drafts can resume that revision after sign-in.
If this step does not work
New edits during a save remain unsaved. For a conflict, review the stored revision. For an uncertain response, Check save status before retrying.
Prepare the decision
Expected result. Enter what needs deciding. For this teaching example, choose Request clarification, explain that the extra quantity needs supporting evidence, and record a concrete next action such as asking for a revised takeoff. Refresh comparison after changing the assessment.
If this step does not work
A clarified question needs an explanation and evidence reference; an assumption needs a reason. Recheck evidence against these versions after confirming questions. Ready for authorization review stays unavailable while server checks report blockers.
Review comparison
Expected result. Name the comparison, choose whether private notes enter the project record, then Save comparison. The result keeps fixed captured inputs.
If this step does not work
Changing estimates requires a fresh review; there is no force overwrite. Saving a comparison is not contractual approval.
Download package (ZIP)
Expected result. Open the saved HTML, CSV or JSON; the package also includes a dictionary, manifest and checksums. Sign out and reopen the same private comparison link.
If this step does not work
The recipient needs project access. A downloaded report does not change the saved comparison.
Estimate-line edits, author-private comparison drafts and immutable final comparisons are different records. There is no financial autosave or browser-stored draft. Use Save draft before browser Back, refreshing or closing this tab; browser warnings may not appear. An expired session can only restore previously saved work.
Reading these steps is learning progress, not proof that an action completed. Check the application's actual saved result. The four original budget, schedule, risk and report lessons below remain separate.
Turn an evidence gap into a useful next action
A useful result explains what is supported, what remains uncertain and the next person’s action. Use this exercise after the historical arithmetic example.
This designed proposal uses historical USD rates as teaching inputs. The CSV has no currency column: choose USD because this lesson explicitly declares it. It is not a real quotation or a current price estimate.
- Use Try historical example to create the untouched three-line Before estimate totaling $47,840. Keep it unchanged. In Cost Estimates, open Practice with an evidence file and Download evidence example (CSV). This exercise imports a separate Proposed estimate.
- Choose Import CSV or Excel, select the file and Inspect file. Set header row 1 and data rows 2 through 3. Map description to column 2, quantity to 3, unit to 4, unit rate to 5, line total to 6 and item code to 1. Leave CSI division unmapped: these item codes are historical source identifiers, not CSI classifications.
- Choose Currency units (major amounts, such as 715.00), Recorded currency USD, and Full estimate to capture both rows in this file. Here, Full means the complete two-row file; it does not establish complete or equivalent project scope. Set Source type to Designed teaching example. Record that this proposal omits portable delineators and deliberately uses LF for channelizers. Preview reviewed import: the two-row subtotal is $47,970.
- Save reviewed import as new estimate when its file-level checks permit it. Choose the historical estimate as Before and the imported estimate as Proposed, then Continue. Open Match rows or declare added / removed work. Explicitly match the channelizer and aggregate descriptions; the baseline source record IDs are 120165 and 260203. Do not declare the unmatched 104 delineators removed merely to clear the warning. A matching description does not resolve LF versus EA.
- Prepare the decision: ask whether the 104 delineators are included, whether channelizers are measured in EA or LF, and what supports increasing aggregate from 56 to 62 CY. The $130 arithmetic difference between $47,840 and $47,970 is not a comparable project change: $4,160 of delineators is absent and the channelizer units conflict. Choose Request clarification, explain those gaps and ask for the inclusion, unit and quantity evidence as the next action.
- Recheck evidence against these versions, then Refresh comparison. Use Save draft to preserve private work, or Review comparison, name it and Save comparison to preserve the conditional assessment. Reopen the result and inspect the HTML report or package: the questions, disposition, reason and next action must remain visible. A question-status change alone cannot fix incompatible inputs.
Optional: complete the controlled scenario
- Save the earlier conditional assessment first. Re-import the same teaching file with the same USD, major-money and row settings. In Correct a captured value with a reason, set source row 2, column 4, replacement EA. Record that this is a controlled teaching correction, not confirmation from a contractor. Preview and save a new estimate.
- In that new estimate, use Add Line for PORTABLE DELINEATORS: unclassified division 00, quantity 104, unit EA, unit rate 40.00. Record source type Designed teaching example, historical source item 120182 in the reference, and that this line is restored solely for the controlled completion. Save the line. Its total is $4,160.
- Start new comparison. Choose the untouched historical Before and the completed teaching Proposed. Continue and explicitly match all three corresponding rows: channelizers, portable delineators and aggregate base. Find historical identifiers in source details when the baseline's item-code field is empty.
- Record the shared three-line teaching scope in the estimate source editor, save it, and refresh the comparison. Explain the hypothetical six additional CY and record a disposition, reason and next action. Recheck evidence against these versions and Refresh comparison again. With all three valid rows matched, expect Proposed $52,130 and change +$4,290. The result remains a constructed scenario, not an observed offer or authorized contract change.
Imports support a bounded CSV/XLSX selection. Original stored values and your reasons remain in the capture; the original file is not retained. Spreadsheet formula results are not recalculated. No assessment sends messages, awards work or approves payment.
Four lessons, one saved workflow
Follow them in order. Open the same instructions above the controls on each project page; you do not need to memorize this guide.
Lesson 1 of 4 · Estimates
Build and check your budget
List the work and its cost so you can explain where the budget comes from.
- Choose an estimate version. The guided sample already has Version 1. For an empty project, choose New empty estimate first.
- Use Add Line to enter work, quantity and unit rate in the declared currency. Use the pencil button to edit an existing line. Low and high costs apply to the whole line, not each unit.
- Save the line, then check the base total and the total with contingency. Record the quotation date, original values and included/excluded work in Evidence for this line, or use the estimate-level source editor for shared scope.
Sample values and expected result. The original sample has three lines: $10,000 preparation, $20,000 electrical and $30,000 installation. Base cost is $60,000; 10% contingency makes $66,000.
Try it yourself. Edit Preparation: keep quantity at 1 and change Unit rate to 12000. Choose Update Line Item. Base cost becomes $62,000 and the total with contingency becomes $68,200. Restore Unit rate to 10000 before the next lesson.
Checkpoint: A saved estimate version containing your line items and budget totals. Reload the page to check that your changes were saved.
Apply this to your own project and understand the limits
Use dated quotations or your own documented estimates. A new version starts empty; it does not copy the previous version's lines.
Contingency is a reserve added to the base budget. It is not a prediction. Low ≤ likely line total ≤ high; blank bounds make a line fixed in the risk model.
Lesson 2 of 4 · Schedule
Work out how long the project takes
Connect activities in the order they must happen, including work that can overlap.
- Choose a schedule version. The sample already contains four activities. For an empty project, choose New empty version, set the start date, then Add activity.
- Enter durations in calendar days. Add a dependency when an activity must wait for another. FS means the earlier activity must finish before this one starts; zero lag adds no extra wait.
- Choose Calculate CPM after saving changes. CPM means critical path method: the longest chain of dependent work determines the finish date.
Sample values and expected result. Preparation takes 2 days. Electrical (3 days) and Installation (5 days) then run in parallel. Inspection takes 1 more day: 2 + max(3, 5) + 1 = 8 calendar days.
Try it yourself. Choose Edit / delay on Installation. Change Most likely from 5 to 6 days, Save activity, then Calculate CPM. The schedule becomes 9 days. Restore 5 days and recalculate before the next lesson.
Checkpoint: A calculated finish date and highlighted critical activities. Saving an activity does not recalculate the schedule; choose Calculate CPM again.
Apply this to your own project and understand the limits
Ask the people doing the work for durations and dependencies. Use the source-notes field to record assumptions. Positive lag adds waiting time after a dependency event.
Leave Baseline alone during this tutorial: it locks the schedule version against editing. Calendar days include weekends; crew availability and holidays are not modeled.
Lesson 3 of 4 · Risk
Explore uncertainty and save the evidence
See a range of possible costs and durations instead of relying on one number.
- In Calculate and save, choose Cost and schedule. Select the estimate and schedule versions you just checked.
- For this tutorial, select 1,000 Simulations and leave Random seed at 12345. Choose Calculate and save. Wait for a Saved result to appear.
- Read the cost and schedule percentiles. Open Assumptions and saved inputs, download the JSON, then choose Replay saved inputs and compare the results.
Sample values and expected result. With the original sample inputs, the middle of the modeled outcomes is near $60,000 and 8 days. The calculation produces the actual values; the tutorial does not insert a canned result.
Try it yourself. Switch between Cost (USD) and Schedule (calendar days). P80 is the value at or below which 80% of these modeled outcomes fall. Compare Replay saved inputs with the original run: saved assumptions and the seed should reproduce it.
Checkpoint: A saved run with both outcomes, exact inputs and a replay setting. Its URL can reopen the result for someone who has access to this project.
Apply this to your own project and understand the limits
After changing an estimate or schedule, use Calculate and save for a new run. Replay deliberately uses the old saved inputs. Use the results to discuss a reserve or a delay, with your assumptions attached.
Cost outcomes exclude contingency. P80 is a model result, not an 80% promise about the real project. Shared inflation, weather and correlated delays are not modeled.
Lesson 4 of 4 · Reports
Explain progress and download a report
Compare work completed, spending and the plan at the same reporting date.
- Choose New Report or Create Report. Select a report period and enter the four dollar amounts below. These progress figures are entered by you; they are not automatically imported from Risk.
- Choose Create Report, then View to inspect the saved progress dashboard. Return to the Reports tab when ready to export.
- Choose Publish and confirm Publish. PDF and Excel buttons then appear. Download a file and reopen the saved report to check it.
Sample values and expected result. Enter Budget at Completion = 60000; Earned Value = 30000; Planned Value to Date = 40000; Actual Cost = 36000. Expect CPI about 0.83, SPI 0.75 and Estimate at Completion $72,000.
Try it yourself. Interpret the example: work worth $30,000 of the budget has cost $36,000, while $40,000 of work was planned by this date. Discuss the overspend and slower progress before making a decision.
Checkpoint: A dated, saved report with performance metrics and downloadable PDF/Excel files. Publishing enables downloads for authorized project members; it does not put the report on a public website.
Apply this to your own project and understand the limits
Use actual spending records and an agreed measure of work completed. Review the draft before publishing. The completion-cost estimate assumes current cost efficiency continues.
Earned value is the budgeted value of completed work, not revenue or a property's selling price. A missing or zero denominator can make a ratio unavailable; do not invent a value to fill the gap.
Plain-language definitions
- Project and version
- A project holds your work. An estimate or schedule version is one saved edition inside it. Creating a new version starts an empty edition; it does not duplicate its predecessor.
- Low / likely / high
- Your plausible minimum, most likely and maximum for one input. For a cost line, use totals for the whole line. Blank bounds are treated as fixed values.
- Contingency
- A budget reserve added to the base estimate. Risk outcomes show base costs before this reserve.
- CPM and critical path
- Critical path method finds the longest chain of dependent work. A delay on that chain can delay the project finish.
- Dependency and lag
- A dependency connects two activities. FS is finish-to-start; SS is start-to-start; FF is finish-to-finish; SF is start-to-finish. Positive lag adds waiting days.
- P50 and P80
- Percentiles of the simulation. Half the modeled outcomes are at or below P50; 80% are at or below P80. Neither is a guarantee.
- Seed and replay
- The seed controls the reproducible random sequence. Replay uses the recorded inputs and environment, even if you later edit the project.
- Distribution, S-Curve and Tornado
- Distribution groups outcomes into ranges. S-Curve shows the cumulative proportion below a value. Tornado compares which modeled inputs most influence the result; it is not proof of causation.
- BAC, EV, PV and AC
- Budget at Completion is the whole budget. Earned Value is the budgeted value of completed work. Planned Value is the budgeted value scheduled by the date. Actual Cost is money spent.
- CPI, SPI and EAC
- CPI = EV ÷ AC; below 1 means spending more than the earned budget. SPI = EV ÷ PV; below 1 means less progress than planned. EAC projects total cost if current cost efficiency continues.
Get unstuck
I signed in, but my projects are missing
This QC preview stores projects separately from the production site. Existing production projects were not copied here. Choose Try the guided sample to create a practice project. Use the same sign-in method each time; another account may have different projects.
I did not receive a text-message code
Check the country code and phone number. Wait for the resend countdown, then try Resend code. If this is your first time using phone sign-in, use Create an account. The code arrives by SMS, not email. Never send your sign-in code to another person.
Google or Facebook returns me to the production site
The preview should keep you in the QC workspace after sign-in. If the address changes to luxury-gating-algo.vercel.app, return to the full preview link and report which sign-in button you used. Repeatedly creating accounts will not repair a redirect.
Calculate and save is disabled
For Cost and schedule, select an estimate version with at least one saved line and a schedule version with at least one activity. Save those inputs first. You can also select Cost only or Schedule only if that is the outcome you need.
I edited an input, but the old result did not change
Saved results preserve the assumptions used at that time. After a schedule edit, choose Calculate CPM again. After changing either version, open Risk and choose Calculate and save for a new run. Replay saved inputs intentionally reproduces the earlier assumptions.
I cannot edit a version or project
A baselined schedule or locked estimate cannot be edited. Choose Create editable revision in Estimates to copy a version, or New empty estimate to start from no lines. A Viewer invitation permits reading and export, while an Editor invitation permits input changes. Ask the project owner to check your access.
Which file should I download?
Risk JSON records the inputs, seed and modeled results for inspection and replay. Report PDF is a readable progress summary. Report Excel contains the reporting values and charts. Review the numbers and assumptions before sharing a file.
How do I invite someone?
Ask them to sign in and copy their account ID from Projects. On your project overview, choose Viewer or Editor and Create invitation. They must accept it in their own workspace. This preview sends no invitation email. You can revoke access from the same overview.
Put the result to work
Use a dated estimate, its assumptions and a saved analysis to discuss a budget reserve, a dependency delay or a progress problem with an owner, contractor or project manager. Replace every teaching input with evidence before using the workflow for a real decision.
This is project planning and reporting. It does not supply live quotations, calibrated loan-default predictions, guaranteed outcomes or evidence that someone will buy the service.